More than a dozen critical Australian Defence Force capability acquisition projects are running years behind schedule under the Morrison Government’s revolving door of Defence Ministers.
Documents obtained under Freedom of Information have revealed schedule blowouts across multi-billion dollar projects which could have a real impact on the ground for Australian Defence Force personnel.
The documents also show the delays have grown worse during 2019, indicating that the Government is failing to manage Defence capability acquisition projects effectively.
In the three months between December 2018 and March 2019, the Government allowed six defence projects worth more than $6 billion to be delayed cumulatively nearly 10 years.
In total, 14 major Defence capability acquisition projects worth $14.99 billion are now running a cumulative 311 months late – more than 25 years.
These include:
The revolving door of Defence Ministers under this Liberal Government is clearly contributing to project blowouts.
In the six years since the Liberals came to office, Defence Ministers have only conducted three Projects of Concern Summits, despite Defence policy stating a Ministerial Summit should be held every six months.
In Parliament this month, the Minister for Defence Industry Melissa Price said: “As the Minister for Defence Industry, my priorities are clear: defence capability is built on time, on budget and on spec.”
These documents show that she is failing to meet her own priorities.
Ministers Reynolds and Price need to stop boasting about defence investment and start delivering the capabilities Australia’s defence personnel need to do their jobs.
Summary – Defence Capability Acquisition and Sustainment Quarterly Performance Report (QPR)
|
Total Budget |
Dec 2018 QPR |
Mar 2019 QPR |
Projects of concern |
|
|
|
Multi-Role Helicopter |
$3,771 m |
28 months late |
29 months late |
Deployable Defence Air Traffic Management and Control System |
$95 m |
40 months late |
40 months late |
Projects of interest |
|
|
|
Amphibious Ships |
$3,092 m |
37 months late |
37 months late |
F-35A Joint Strike Fighter |
$16,524 m |
Nil slippage |
Nil slippage |
Civil Military Air Traffic Management System |
$976 m |
Nil slippage |
4 months late |
Battlefield Command System |
$960 m |
7 months late |
12 months late |
Protected Mobility Vehicle – Light (Hawkei) |
$1,980 m |
Nil slippage |
12 months late |
Pilot Training System |
$1,245 m |
Degraded IOC |
13 months late |
ADF Identification Friend or Foe and ADS Broadcast |
$436 m |
28 months |
28 months |
Defence Satellite Communications Capability Phase5A |
$422 m |
24 months |
42 months |
Airborne Early Warning and Control Upgrade |
$1,191 m |
12 months |
12 months |
Maritime Operational Support Capability |
$1,071 m |
redacted |
No slippage |
Special Operations Vehicle fleets |
$332 m |
redacted |
40 months late |
Rapid Environmental Assessment |
$46 m |
15 months |
12 months |
Hercules C-130J Block Upgrade |
$238 m |
Redacted |
18 months |
Fixed Defence Air Traffic Control Surveillance Sensors |
$202 m |
22 months |
12 months |